| Assessment Year | 2013 |
|---|---|
| Principal Product | Licorice Candy |
| NAICS | 311340: Nonchocolate Confectionery Manufacturing |
| SIC | 2064: Candy and Other Confectionery Products |
| Sales Range | $50 M to 100M |
| # of Employees | 186 |
| Plant Area |
250,000
ft2
|
| Annual Production | 379
lb
|
| Production Hrs. Annual | 6,554
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $548,359 | 5,634,410 |
kWh
|
$0.097 |
| Electricity Demand | $236,777 | 14,448 |
kW-mo/yr
|
$16.39 |
| Electricity Fees | $27,154 | - |
|
- |
| Natural Gas | $853,717 | 139,785 |
MMBtu
|
$6.11 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $284,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,233 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1212: Operate boilers on high fire setting | $18,109 | - |
$2,040
20,957
kWh
|
$679
-
kW-mo/yr
|
- |
$15,390
-
MMBtu
|
|
| 02 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $578 | $810 | - | - | - |
$578
-
MMBtu
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,006 | $16,020 |
$5,799
59,586
kWh
|
$1,207
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $14,210 | $38,634 |
$11,066
133,708
kWh
|
$3,144
-
kW-mo/yr
|
- | - | |
| 05 | 2.4227: Use compressor air filters | $9,736 | $36,817 |
$9,736
100,035
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $919 | $5,601 |
$919
9,439
kWh
|
- | - | - | |
| 07 | 2.3132: Recharge batteries on during off-peak demand periods | $4,991 | - | - | - | $4,991 | - | |
| 08 | 2.2437: Recover waste heat from equipment | $228,512 | - | - | - | - |
$228,512
-
MMBtu
|
|
| TOTAL RECOMMENDED | $284,061 | $97,882 |
$29,560
323,725
kWh
|
$5,030
-
kW-mo/yr
|
$4,991 |
$244,480
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $11,233 | $43,228 |
$10,655
109,474
kWh
|
- | - |
$578
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs