Assessment Year | 2012 |
---|---|
Principal Product | Salami and Specialty Italian Meats |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
75,000
ft2
|
Annual Production | 12,000,000
lb
|
Production Hrs. Annual | 4,930
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $482,744 | 5,771,839 |
kWh
|
$0.084 |
Electricity Demand | $257,489 | 12,371 |
kW-mo/yr
|
$20.81 |
Electricity Fees | $12,627 | - |
|
- |
Natural Gas | $205,822 | 29,805 |
MMBtu
|
$6.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $126,257 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $3,969 | - |
$2,381
28,484
kWh
|
- |
$1,588
-
MMBtu
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $642 | $43 |
$450
5,378
kWh
|
$192
-
kW-mo/yr
|
- | - | - | |
03 | 2.2691: Shut off cooling if cold outside air will cool process | $36,414 | $12,500 |
$36,414
435,573
kWh
|
- | - | - | - | |
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $47,040 | $16,100 |
$47,040
562,685
kWh
|
- | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $662 | $228 |
$276
3,296
kWh
|
$386
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $9,464 | $10,283 | - | - |
$9,464
-
MMBtu
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $2,287 | $3,924 |
$1,538
18,396
kWh
|
$749
-
kW-mo/yr
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $1,288 | $3,390 |
$569
6,802
kWh
|
$719
-
kW-mo/yr
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,693 | $31,027 |
$5,467
65,391
kWh
|
$2,183
-
kW-mo/yr
|
- | $783 | $260 | |
10 | 4.212: Adopt in-house material generation | $15,798 | $22,322 | - | - | - | - | $15,798 | |
TOTAL RECOMMENDED | $126,257 | $99,817 |
$94,135
1,126,005
kWh
|
$4,229
-
kW-mo/yr
|
$11,052
-
MMBtu
|
$783 | $16,058 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs