ITAC Assessment: SF0411
ITAC logo
ITAC Assessment: SF0411
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Packaged Lamb
NAICS 112112: Cattle Feedlots
SIC 2011: Meat Packing Plants
Sales Range $100
M
to 500
M
# of Employees 146
Plant Area 300,000
ft2
Annual Production 285,600
pieces
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $473,261 5,132,994
kWh
Electricity Demand $216,306 11,748
kW-mo/yr
Electricity Fees $9,842 -
Natural Gas $99,372 19,662
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $136,292 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $94,322

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.8112: Combine utility meters $35,266 - - - $35,266 - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,097 $504 $3,097
33,660
kWh
- - - - -
03 2.6223: Schedule use of elevators to conserve energy $716 - - - $716 - - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $1,666 $1,200 - - - $1,666
-
MMBtu
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $19,104 $6,660 $19,104
207,654
kWh
- - - - -
06 2.4322: Use or replace with energy efficient substitutes $1,094 $939 $851
9,255
kWh
$243
-
kW-mo/yr
- - - -
07 2.2627: Use multiple-effect evaporators $14,245 $17,433 $11,182
121,541
kWh
$3,063
-
kW-mo/yr
- - - -
08 2.2437: Recover waste heat from equipment $2,723 $3,965 - - - $2,723
-
MMBtu
- -
09 2.2414: Use waste heat from hot flue gases to preheat $4,671 $11,216 - - - $4,671
-
MMBtu
- -
10 2.7135: Install occupancy sensors $18,497 $47,901 $13,878
150,843
kWh
$4,619
-
kW-mo/yr
- - - -
11 2.2622: Replace existing chiller with high efficiency model $1,227 $3,774 $963
10,473
kWh
$264
-
kW-mo/yr
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $33,986 $135,330 $22,857
248,440
kWh
$9,284
-
kW-mo/yr
- - $886 $959
TOTAL RECOMMENDED $136,292 $228,922 $71,932
781,866
kWh
$17,473
-
kW-mo/yr
$35,982 $9,060
-
MMBtu
$886 $959
TOTAL IMPLEMENTED $94,322 $185,874 $40,683
442,198
kWh
$14,146
-
kW-mo/yr
$35,982 $1,666
-
MMBtu
$886 $959
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs