Assessment Year | 2012 |
---|---|
Principal Product | Packaged Lamb |
NAICS | 112112: Cattle Feedlots |
SIC | 2011: Meat Packing Plants |
Sales Range | $100 M to 500M |
# of Employees | 146 |
Plant Area |
300,000
ft2
|
Annual Production | 285,600
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $473,261 | 5,132,994 |
kWh
|
$0.092 |
Electricity Demand | $216,306 | 11,748 |
kW-mo/yr
|
$18.41 |
Electricity Fees | $9,842 | - |
|
- |
Natural Gas | $99,372 | 19,662 |
MMBtu
|
$5.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $136,292 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $94,322 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $35,266 | - | - | - | $35,266 | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,097 | $504 |
$3,097
33,660
kWh
|
- | - | - | - | - | |
03 | 2.6223: Schedule use of elevators to conserve energy | $716 | - | - | - | $716 | - | - | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,666 | $1,200 | - | - | - |
$1,666
-
MMBtu
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,104 | $6,660 |
$19,104
207,654
kWh
|
- | - | - | - | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $1,094 | $939 |
$851
9,255
kWh
|
$243
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.2627: Use multiple-effect evaporators | $14,245 | $17,433 |
$11,182
121,541
kWh
|
$3,063
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $2,723 | $3,965 | - | - | - |
$2,723
-
MMBtu
|
- | - | |
09 | 2.2414: Use waste heat from hot flue gases to preheat | $4,671 | $11,216 | - | - | - |
$4,671
-
MMBtu
|
- | - | |
10 | 2.7135: Install occupancy sensors | $18,497 | $47,901 |
$13,878
150,843
kWh
|
$4,619
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.2622: Replace existing chiller with high efficiency model | $1,227 | $3,774 |
$963
10,473
kWh
|
$264
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $33,986 | $135,330 |
$22,857
248,440
kWh
|
$9,284
-
kW-mo/yr
|
- | - | $886 | $959 | |
TOTAL RECOMMENDED | $136,292 | $228,922 |
$71,932
781,866
kWh
|
$17,473
-
kW-mo/yr
|
$35,982 |
$9,060
-
MMBtu
|
$886 | $959 | ||
TOTAL IMPLEMENTED | $94,322 | $185,874 |
$40,683
442,198
kWh
|
$14,146
-
kW-mo/yr
|
$35,982 |
$1,666
-
MMBtu
|
$886 | $959 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs