ITAC Assessment: SF0406
ITAC logo
ITAC Assessment: SF0406
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Candy(Chocolate and Yogurt)
NAICS 311352: Confectionery Manufacturing from Purchased Chocolate
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 300,000
ft2
Annual Production 2,000,000
units
Production Hrs. Annual 6,936
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $531,380 7,979,320
kWh
Electricity Demand $302,644 17,088
kW-mo/yr
Natural Gas $233,179 47,236
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $169,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,836

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,385 - $7,385
110,890
kWh
- -
02 2.7224: Reduce space conditioning during non-working hours $10,401 - $6,314
94,806
kWh
- $4,087
-
MMBtu
03 2.2122: Install / repair insulation on condensate lines $2,483 - - - $2,483
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $17,629 $818 $12,074
181,291
kWh
$5,555
-
kW-mo/yr
-
05 2.7111: Reduce illumination to minimum necessary levels $7,567 $3,773 $5,183
77,822
kWh
$2,384
-
kW-mo/yr
-
06 2.7132: Install timers on light switches in little used areas $1,352 $1,460 $926
13,903
kWh
$426
-
kW-mo/yr
-
07 2.2612: Use cooling tower water instead of refrigeration $90,076 $288,023 $62,725
941,818
kWh
$27,351
-
kW-mo/yr
-
08 2.1223: Install smaller boiler (increase high fire duty cycle) $25,304 $93,999 $2,684
40,305
kWh
$1,239
-
kW-mo/yr
$21,381
-
MMBtu
09 2.1243: Use heat from boiler blowdown to preheat boiler feed water $2,696 $10,439 - - $2,696
-
MMBtu
10 2.7135: Install occupancy sensors $4,954 $21,408 $2,630
39,486
kWh
$2,324
-
kW-mo/yr
-
TOTAL RECOMMENDED $169,847 $419,920 $99,921
1,500,321
kWh
$39,279
-
kW-mo/yr
$30,647
-
MMBtu
TOTAL IMPLEMENTED $27,836 $3,773 $18,882
283,518
kWh
$2,384
-
kW-mo/yr
$6,570
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs