| Assessment Year | 2011 |
|---|---|
| Principal Product | Seals and Gaskets |
| NAICS | 339991: Gasket, Packing, and Sealing Device Manufacturing |
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 43 |
| Plant Area |
100,000
ft2
|
| Annual Production | 120,000
lb
|
| Production Hrs. Annual | 2,470
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $63,637 | 653,760 |
kWh
|
$0.097 |
| Electricity Demand | $20,916 | 2,326 |
kW-mo/yr
|
$8.99 |
| Electricity Fees | $684 | - |
|
- |
| Natural Gas | $15,192 | 1,665 |
MMBtu
|
$9.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,889 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7134: Use photocell controls | $1,438 | $3,737 |
$1,050
10,795
kWh
|
$388
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $2,857 | $10,811 |
$2,142
22,019
kWh
|
$788
-
kW-mo/yr
|
- | $(-120.0) | $47 | |
| 03 | 2.7141: Lower light fixtures in high ceiling areas | $5,402 | $23,288 |
$3,977
40,869
kWh
|
$1,470
-
kW-mo/yr
|
- | $(-200.0) | $155 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,789 | $29,916 |
$3,619
37,190
kWh
|
$680
-
kW-mo/yr
|
- | $353 | $137 | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $766 | $4,483 |
$797
8,190
kWh
|
$283
-
kW-mo/yr
|
$(-314.0)
-
MMBtu
|
- | - | |
| 06 | 2.4131: Size electric motors for peak operating efficiency | $1,637 | $11,070 |
$1,637
16,824
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $16,889 | $83,305 |
$13,222
135,887
kWh
|
$3,609
-
kW-mo/yr
|
$(-314.0)
-
MMBtu
|
$33 | $339 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs