Assessment Year | 1995 |
---|---|
Principal Product | Composite Cans |
NAICS |
n/a
|
SIC | 2655: Fiber Cans, Tubes, Drums, and Similar Products |
Sales Range | $10 M to 50M |
# of Employees | 77 |
Plant Area |
164,000
ft2
|
Annual Production | 270,000,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $250,949 | 2,495,604 |
kWh
|
$0.10 |
Natural Gas | $15,661 | 2,060 |
MMBtu
|
$7.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,204 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,729 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $5,729 | $4,910 |
$5,729
56,858
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,762 | $14,570 |
$7,762
77,081
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $938 | $920 |
$938
9,379
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,423 | $45,026 |
$18,423
186,108
kWh
|
- | |
05 | 2.7144: Install spectral reflectors / delamp | $2,269 | $3,995 |
$2,269
21,395
kWh
|
- | |
06 | 2.7135: Install occupancy sensors | $833 | $1,026 |
$833
7,620
kWh
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $23,250 | $2,000 | - |
$23,250
-
lb
|
|
TOTAL RECOMMENDED | $59,204 | $72,447 |
$35,954
358,441
kWh
|
$23,250
-
lb
|
||
TOTAL IMPLEMENTED | $5,729 | $4,910 |
$5,729
56,858
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs