ITAC Assessment: SF0384
ITAC logo
ITAC Assessment: SF0384
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Food Products- Canned Beans & Hominy
NAICS 311421: Fruit and Vegetable Canning
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 250,000
ft2
Annual Production 3,600,000
units
Production Hrs. Annual 5,150
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $225,589 2,717,938
kWh
Electricity Demand $101,012 8,428
kW-mo/yr
Electricity Fees $22,610 -
Natural Gas $617,067 125,850
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $173,716 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $164,443

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.2135: Repair and eliminate steam leaks $65,311 - - - $65,311
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $806 - $1,166
11,133
kWh
- - $(-360.0)
03 2.4231: Reduce the pressure of compressed air to the minimum required $450 - $277
3,331
kWh
$173
-
kW-mo/yr
- -
04 2.2122: Install / repair insulation on condensate lines $70,630 $14,698 - - $70,630
-
MMBtu
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $94 $48 $53
636
kWh
$41
-
kW-mo/yr
- -
06 2.4133: Use most efficient type of electric motors $6,925 $4,309 $4,490
53,941
kWh
$2,435
-
kW-mo/yr
- -
07 2.2136: Install / repair insulation on steam lines $8,056 $11,016 - - $8,056
-
MMBtu
-
08 2.7135: Install occupancy sensors $4,074 $8,348 $2,692
32,343
kWh
$1,382
-
kW-mo/yr
- -
09 2.4239: Eliminate or reduce compressed air usage $5,199 $14,850 $2,840
34,121
kWh
$2,359
-
kW-mo/yr
- -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $12,171 $37,229 $7,615
91,482
kWh
$4,556
-
kW-mo/yr
- -
TOTAL RECOMMENDED $173,716 $90,498 $19,133
226,987
kWh
$10,946
-
kW-mo/yr
$143,997
-
MMBtu
$(-360.0)
TOTAL IMPLEMENTED $164,443 $67,300 $13,601
160,523
kWh
$7,205
-
kW-mo/yr
$143,997
-
MMBtu
$(-360.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs