Assessment Year | 2010 |
---|---|
Principal Product | Chocolate |
NAICS | 311351: Chocolate and Confectionery Manufacturing from Cacao Beans |
SIC | 2066: Chocolate and Cocoa Products |
Sales Range | $100 M to 500M |
# of Employees | 110 |
Plant Area |
120,000
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,403,559 | 16,486,181 |
kWh
|
$0.085 |
Electricity Demand | $469,385 | 78,217 |
kW-mo/yr
|
$6.00 |
Natural Gas | $393,703 | 33,144 |
MMBtu
|
$11.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $288,381 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,723 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $9,146 | $2,700 | - | - |
$9,146
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,775 | $7,837 |
$10,775
114,199
kWh
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,878 | $1,247 |
$1,878
14,994
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $53,897 | $49,178 |
$49,126
520,682
kWh
|
$4,771
-
kW-mo/yr
|
- | |
05 | 2.7134: Use photocell controls | $4,141 | $6,637 |
$4,141
33,355
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $4,265 | $8,098 |
$4,265
45,252
kWh
|
- | - | |
07 | 2.4234: Cool compressor air intake with heat exchanger | $10,035 | $18,281 |
$10,035
106,355
kWh
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,262 | $14,381 |
$7,262
76,965
kWh
|
- | - | |
09 | 2.2314: Replace heat treating oven with more efficient unit | $165,218 | $158,868 |
$150,474
1,594,844
kWh
|
$14,744
-
kW-mo/yr
|
- | |
10 | 2.7135: Install occupancy sensors | $12,608 | $36,493 |
$12,608
119,278
kWh
|
- | - | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $733 | $2,953 |
$733
7,773
kWh
|
- | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,423 | $62,855 |
$8,423
77,248
kWh
|
- | - | |
TOTAL RECOMMENDED | $288,381 | $369,528 |
$259,720
2,710,945
kWh
|
$19,515
-
kW-mo/yr
|
$9,146
-
MMBtu
|
||
TOTAL IMPLEMENTED | $99,723 | $168,653 |
$85,806
872,535
kWh
|
$4,771
-
kW-mo/yr
|
$9,146
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs