Assessment Year | 2009 |
---|---|
Principal Product | ENGINEERED BUILDINGS |
NAICS | 332311: Prefabricated Metal Building and Component Manufacturing |
SIC | 3448: Prefabricated Metal Buildings and Components |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
107,000
ft2
|
Annual Production | 11,529
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $130,977 | 1,158,880 |
kWh
|
$0.11 |
Electricity Demand | $32,797 | 4,380 |
kW-mo/yr
|
$7.49 |
Electricity Fees | $1,435 | - |
|
- |
Natural Gas | $823 | 70 |
MMBtu
|
$11.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,888 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,752 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,329 | - |
$9,329
72,660
kWh
|
- | - | |
02 | 2.4235: Remove or close off unneeded compressed air lines | $909 | - |
$909
7,076
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,136 | $1,566 |
$1,760
13,710
kWh
|
$376
-
kW-mo/yr
|
- | |
04 | 2.7134: Use photocell controls | $8,945 | $5,833 |
$6,993
54,499
kWh
|
$1,952
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $3,347 | $4,920 |
$2,646
20,605
kWh
|
$701
-
kW-mo/yr
|
- | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $803 | $1,288 |
$1,122
8,736
kWh
|
$114
-
kW-mo/yr
|
$(-433.0)
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,419 | $28,144 |
$4,369
34,027
kWh
|
$1,050
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $30,888 | $41,751 |
$27,128
211,313
kWh
|
$4,193
-
kW-mo/yr
|
$(-433.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $28,752 | $40,185 |
$25,368
197,603
kWh
|
$3,817
-
kW-mo/yr
|
$(-433.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs