| Assessment Year | 2009 |
|---|---|
| Principal Product | Railroad Waste Treatment Systems |
| NAICS | 336510: Railroad Rolling Stock Manufacturing |
| SIC | 3743: Railroad Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 55 |
| Plant Area |
70,000
ft2
|
| Annual Production | 250
units
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $53,732 | 497,680 |
kWh
|
$0.11 |
| Electricity Demand | $17,199 | 2,466 |
kW-mo/yr
|
$6.97 |
| Natural Gas | $41,657 | 3,655 |
MMBtu
|
$11.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,359 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,324 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,324 | - |
$3,324
33,336
kWh
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $1,657 | $1,518 |
$1,258
10,373
kWh
|
$399
-
kW-mo/yr
|
- | |
| 03 | 2.7231: Use radiant heater for spot heating | $1,094 | $2,088 |
$804
6,630
kWh
|
$290
-
kW-mo/yr
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $209 | $587 |
$167
1,028
kWh
|
$42
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $977 | $4,281 |
$718
5,920
kWh
|
$259
-
kW-mo/yr
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,529 | $30,407 |
$6,529
53,829
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,453 | $38,867 |
$3,436
28,327
kWh
|
$1,017
-
kW-mo/yr
|
- | |
| 08 | 2.7232: Replace existing hvac unit with high efficiency model | $2,116 | $25,320 |
$1,368
11,279
kWh
|
$378
-
kW-mo/yr
|
$370
-
MMBtu
|
|
| TOTAL RECOMMENDED | $20,359 | $103,068 |
$17,604
150,722
kWh
|
$2,385
-
kW-mo/yr
|
$370
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,324 | - |
$3,324
33,336
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs