Assessment Year | 2008 |
---|---|
Principal Product | Bottled Wine |
NAICS | 312130: Wineries |
SIC | 2084: Wines, Brandy, and Brandy Spirits |
Sales Range | $100 M to 500M |
# of Employees | 241 |
Plant Area |
230,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 4,020
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $401,548 | 16,890 |
kWh
|
$23.77 |
Electricity Demand | $153,417 | 11,671 |
kW-mo/yr
|
$13.15 |
Electricity Fees | $13,195 | - |
|
- |
Natural Gas | $151,347 | 15,169 |
MMBtu
|
$9.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $138,296 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $74,092 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,321 | $150 |
$5,321
52,472
kWh
|
- | - | - | |
02 | 2.3113: Make ice during off peak hours for cooling | $41,503 | - | - | - | - | $41,503 | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,655 | $6,281 |
$6,655
80,413
kWh
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $2,504 | $3,760 | - | - |
$2,504
-
MMBtu
|
- | |
05 | 2.7212: Install or upgrade insulation on hvac distribution systems | $17,740 | $26,898 |
$17,740
213,716
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $37,472 | $80,535 |
$23,011
280,345
kWh
|
$14,461
-
kW-mo/yr
|
- | - | |
07 | 2.2628: Utilize a less expensive cooling method | $4,534 | $10,979 |
$3,897
43,924
kWh
|
$637
-
kW-mo/yr
|
- | - | |
08 | 3.4111: Use closed cycle process to minimize waste water production | $1,532 | $4,549 |
$1,532
19,975
kWh
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,225 | $40,545 |
$9,695
118,119
kWh
|
$2,530
-
kW-mo/yr
|
- | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $8,810 | $36,311 |
$6,727
8,959
kWh
|
$2,083
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $138,296 | $210,008 |
$74,578
817,923
kWh
|
$19,711
-
kW-mo/yr
|
$2,504
-
MMBtu
|
$41,503 | ||
TOTAL IMPLEMENTED | $74,092 | $154,259 |
$57,101
692,593
kWh
|
$16,991
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs