Assessment Year | 2006 |
---|---|
Principal Product | Garlic Products |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $100 M to 500M |
# of Employees | 600 |
Plant Area |
410,000
ft2
|
Annual Production | 2,000,000
ton
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $820,043 | 11,062,460 |
kWh
|
$0.074 |
Electricity Demand | $141,436 | 28,070 |
kW-mo/yr
|
$5.04 |
Natural Gas | $307,444 | 36,879 |
MMBtu
|
$8.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $214,493 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $65,964 | $9,840 |
$54,212
649,472
kWh
|
$11,752
-
kW-mo/yr
|
- | - | |
02 | 2.4227: Use compressor air filters | $3,806 | $1,200 |
$3,226
38,666
kWh
|
$580
-
kW-mo/yr
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $13,592 | $4,815 |
$11,570
138,624
kWh
|
$2,022
-
kW-mo/yr
|
- | - | |
04 | 2.2136: Install / repair insulation on steam lines | $1,439 | $600 | - | - |
$1,439
-
MMBtu
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $9,301 | $4,440 |
$8,372
104,617
kWh
|
$929
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,924 | $17,809 |
$20,970
251,230
kWh
|
$1,954
-
kW-mo/yr
|
- | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $22,820 | $20,775 | - | - | - | $22,820 | |
08 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,123 | $5,680 |
$1,869
1,033
kWh
|
$1,254
-
kW-mo/yr
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,235 | $12,934 |
$6,401
76,686
kWh
|
$1,834
-
kW-mo/yr
|
- | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $642 | $1,153 |
$541
6,484
kWh
|
$101
-
kW-mo/yr
|
- | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $667 | $1,280 |
$557
6,675
kWh
|
$110
-
kW-mo/yr
|
- | - | |
12 | 2.2414: Use waste heat from hot flue gases to preheat | $4,895 | $10,000 | - | - |
$4,895
-
MMBtu
|
- | |
13 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $40,083 | $84,065 |
$34,131
408,910
kWh
|
$5,952
-
kW-mo/yr
|
- | - | |
14 | 2.8114: Change rate schedules or other changes in utility service | $7,844 | $20,775 | - | - | - | $7,844 | |
15 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,554 | $23,579 |
$6,233
74,674
kWh
|
$1,321
-
kW-mo/yr
|
- | - | |
16 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,604 | $6,397 |
$1,325
15,875
kWh
|
$279
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $214,493 | $225,342 |
$149,407
1,772,946
kWh
|
$28,088
-
kW-mo/yr
|
$6,334
-
MMBtu
|
$30,664 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs