| Assessment Year | 2005 |
|---|---|
| Principal Product | Bell Pepper |
| NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
160,000
ft2
|
| Annual Production | 7,599
ton
|
| Production Hrs. Annual | 2,952
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $382,493 | 10,259,618 |
kWh
|
$0.037 |
| Electricity Demand | $287,197 | 24,484 |
kW-mo/yr
|
$11.73 |
| Natural Gas | $74,289 | 10,360 |
MMBtu
|
$7.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,168 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7134: Use photocell controls | $5,334 | $5,796 |
$3,737
91,157
kWh
|
$1,597
-
kW-mo/yr
|
- | |
| 02 | 2.7135: Install occupancy sensors | $827 | $4,059 |
$826
20
kWh
|
$1
-
kW-mo/yr
|
- | |
| 03 | 2.7134: Use photocell controls | $1,174 | $2,280 |
$533
12
kWh
|
$641
-
kW-mo/yr
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $3 | $8,530 |
$2
49
kWh
|
$1
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3 | $11,928 |
$2
59
kWh
|
$1
-
kW-mo/yr
|
- | |
| 06 | 2.2628: Utilize a less expensive cooling method | $20 | $80,000 |
$12
247
kWh
|
$8
-
kW-mo/yr
|
- | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $818 | $3,200 |
$483
11,779
kWh
|
$335
-
kW-mo/yr
|
- | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $13 | $10,000 | - | - |
$13
-
lb
|
|
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4 | $16,945 | - | - |
$4
-
lb
|
|
| TOTAL RECOMMENDED | $8,196 | $142,738 |
$5,595
103,323
kWh
|
$2,584
-
kW-mo/yr
|
$17
-
lb
|
||
| TOTAL IMPLEMENTED | $6,168 | $27,526 |
$4,222
102,985
kWh
|
$1,933
-
kW-mo/yr
|
$13
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs