Assessment Year | 2005 |
---|---|
Principal Product | Poultry Feed |
NAICS | 311119: Other Animal Food Manufacturing |
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 15 |
Plant Area |
217,800
ft2
|
Annual Production | 182,000
ton
|
Production Hrs. Annual | 6,656
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $242,442 | 3,634,781 |
kWh
|
$0.067 |
Electricity Demand | $76,626 | 11,473 |
kW-mo/yr
|
$6.68 |
Natural Gas | $166,148 | 25,680 |
MMBtu
|
$6.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,842 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,719 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $679 | - |
$679
16,496
kWh
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,124 | $948 |
$1,452
22,277
kWh
|
$321
-
kW-mo/yr
|
- | $351 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,170 | $771 |
$906
11,351
kWh
|
$264
-
kW-mo/yr
|
- | - | |
04 | 2.2136: Install / repair insulation on steam lines | $1,983 | $1,979 | - | - |
$1,983
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $187 | $480 |
$156
2,396
kWh
|
$31
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $1,140 | $3,079 |
$759
11,646
kWh
|
$381
-
kW-mo/yr
|
- | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $12,370 | $50,000 | - | - |
$12,370
-
MMBtu
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,189 | $5,346 |
$994
15,253
kWh
|
$195
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $20,842 | $62,603 |
$4,946
79,419
kWh
|
$1,192
-
kW-mo/yr
|
$14,353
-
MMBtu
|
$351 | ||
TOTAL IMPLEMENTED | $17,719 | $57,545 |
$4,187
67,773
kWh
|
$811
-
kW-mo/yr
|
$12,370
-
MMBtu
|
$351 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs