ITAC Assessment: SF0308
ITAC logo
ITAC Assessment: SF0308
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Poultry Products
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 60,000
ft2
Annual Production 780,000
pieces
Production Hrs. Annual 2,730
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $106,522 676,120
kWh
Natural Gas $55,292 6,163
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,364 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,320

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2135: Repair and eliminate steam leaks $1,671 - - - $1,671
-
MMBtu
02 2.7124: Make a practice of turning off lights when not needed $521 - $459
3,527
kWh
$62
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $1,198 $430 $1,070
7,228
kWh
$128
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,813 $1,512 $1,613
11,408
kWh
$200
-
kW-mo/yr
-
05 2.1121: Use insulation in furnaces to facilitate heating / cooling $325 $415 - - $325
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,381 $9,206 $2,114
14,964
kWh
$267
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $455 $1,925 $455
3,219
kWh
- -
TOTAL RECOMMENDED $8,364 $13,488 $5,711
40,346
kWh
$657
-
kW-mo/yr
$1,996
-
MMBtu
TOTAL IMPLEMENTED $6,320 $12,643 $4,182
29,591
kWh
$467
-
kW-mo/yr
$1,671
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs