ITAC Assessment: SF0304
ITAC logo
ITAC Assessment: SF0304
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Metal Cabinets for Technology Companies
NAICS 332439: Other Metal Container Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 65,000
ft2
Annual Production 13,440
ton
Production Hrs. Annual 4,394
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $183,321 1,207,040
kWh
Electricity Demand $18,622 4,204
kW-mo/yr
Natural Gas $29,594 3,343
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,265 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,751

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
01 2.6218: Turn off equipment when not in use $17,326 - $17,326
138,840
kWh
- - - -
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $871 - - - $871
-
MMBtu
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,751 - $3,751
33,527
kWh
- - - -
04 2.6218: Turn off equipment when not in use $2,623 - $2,623
21,018
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,248 $499 $1,119
8,964
kWh
$129
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $465 $588 $301
2,411
kWh
$16
-
kW-mo/yr
- $85 $63
07 2.7135: Install occupancy sensors $598 $848 $467
3,745
kWh
$131
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $1,062 $1,832 $952
7,625
kWh
$110
-
kW-mo/yr
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $4,442 $19,385 $3,981
31,901
kWh
$461
-
kW-mo/yr
- - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,879 $12,894 $2,580
20,678
kWh
$299
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $35,265 $36,046 $33,100
268,709
kWh
$1,146
-
kW-mo/yr
$871
-
MMBtu
$85 $63
TOTAL IMPLEMENTED $3,751 - $3,751
33,527
kWh
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs