Assessment Year | 2004 |
---|---|
Principal Product | Printed Circuit Board Assembly |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
53,715
ft2
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $543,594 | 5,267,600 |
kWh
|
$0.10 |
Natural Gas | $3,304 | 3,284 |
MMBtu
|
$1.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,079 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,189 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $4,565 | $273 |
$4,565
48,266
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $2,670 | $949 |
$2,206
23,304
kWh
|
$464
-
kW-mo/yr
|
|
03 | 2.8114: Change rate schedules or other changes in utility service | $57,647 | $31,100 |
$57,647
-
kWh
|
- | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,975 | $2,706 |
$3,349
35,381
kWh
|
$626
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,974 | $3,208 |
$2,486
26,257
kWh
|
$488
-
kW-mo/yr
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $545 | $855 |
$441
4,654
kWh
|
$104
-
kW-mo/yr
|
|
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $423 | $715 |
$356
3,784
kWh
|
$67
-
kW-mo/yr
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,280 | $8,246 |
$4,280
45,217
kWh
|
- | |
TOTAL RECOMMENDED | $77,079 | $48,052 |
$75,330
186,863
kWh
|
$1,749
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $6,189 | $5,012 |
$5,133
54,215
kWh
|
$1,056
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs