Assessment Year | 2004 |
---|---|
Principal Product | Newspapers |
NAICS | 511110: Newspaper Publishers |
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
84,000
ft2
|
Annual Production | 74,000,000
pieces
|
Production Hrs. Annual | 4,108
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $386,210 | 3,871,255 |
kWh
|
$0.100 |
Electricity Demand | $130,729 | 11,584 |
kW-mo/yr
|
$11.29 |
Natural Gas | $46,147 | 5,425 |
MMBtu
|
$8.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $132,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $522 | - |
$906
9,554
kWh
|
- | $(-384.0) | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,943 | $1,085 |
$1,647
18,190
kWh
|
$296
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $3,803 | $2,432 |
$3,262
34,409
kWh
|
$541
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $61,229 | $55,977 |
$52,687
555,825
kWh
|
$8,542
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,856 | $24,003 |
$9,980
105,291
kWh
|
$6,876
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,297 | $15,944 |
$3,196
33,710
kWh
|
$1,101
-
kW-mo/yr
|
- | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $43,910 | $29,800 | - | - | - | $43,910 | |
TOTAL RECOMMENDED | $132,560 | $129,241 |
$71,678
756,979
kWh
|
$17,356
-
kW-mo/yr
|
$(-384.0) | $43,910 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs