ITAC Assessment: SF0281
ITAC logo
ITAC Assessment: SF0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Ceramic Dinner Ware and Tiles
NAICS 327120: Clay Building Material and Refractories Manufacturing
SIC 3258:
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 30,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 2,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,101 204,080
kWh
Natural Gas $62,420 8,216
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,509 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4226: Use / purchase optimum sized compressor $1,183 $233 $1,183
7,298
kWh
-
02 2.7134: Use photocell controls $1,246 $1,800 $1,246
7,800
kWh
-
03 2.1121: Use insulation in furnaces to facilitate heating / cooling $2,651 $4,263 - $2,651
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,270 $5,700 $2,270
16,780
kWh
-
05 2.7145: Install skylights $219 $640 $219
1,352
kWh
-
06 2.4133: Use most efficient type of electric motors $940 $3,016 $940
5,798
kWh
-
TOTAL RECOMMENDED $8,509 $15,652 $5,858
39,028
kWh
$2,651
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs