Assessment Year | 2004 |
---|---|
Principal Product | Canned Olives |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $5 M to 10M |
# of Employees | 55 |
Plant Area |
150,000
ft2
|
Annual Production | 0
lb
|
Production Hrs. Annual | 2,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $256,587 | 1,711,214 |
kWh
|
$0.15 |
Natural Gas | $680,244 | 121,851 |
MMBtu
|
$5.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $118,216 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,074 | - | n/a |
$8,074
58,019
kWh
|
- |
02 | 2.2135: Repair and eliminate steam leaks | $3,660 | $312 | n/a | - |
$3,660
-
MMBtu
|
03 | 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat | $65,362 | $60,000 | n/a |
$65,362
435,923
kWh
|
- |
04 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $1,624 | $1,887 | n/a |
$1,624
10,834
kWh
|
- |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $290 | $454 | n/a |
$290
1,932
kWh
|
- |
06 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $1,847 | $3,074 | n/a | - |
$1,847
-
MMBtu
|
07 | 2.2136: Install / repair insulation on steam lines | $13,285 | $24,474 | n/a | - |
$13,285
-
MMBtu
|
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,293 | $2,800 | n/a |
$1,293
8,625
kWh
|
- |
09 | 2.7135: Install occupancy sensors | $1,230 | $3,840 | n/a |
$1,230
8,206
kWh
|
- |
10 | 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat | $13,726 | $60,000 | n/a |
$13,726
91,544
kWh
|
- |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,825 | $34,552 | n/a |
$7,825
48,708
kWh
|
- |
TOTAL RECOMMENDED | $118,216 | $191,393 |
$99,424
663,791
kWh
|
$18,792
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs