ITAC Assessment: SF0278
ITAC logo
ITAC Assessment: SF0278
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Canned Olives
NAICS 311421: Fruit and Vegetable Canning
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 150,000
ft2
Annual Production 0
lb
Production Hrs. Annual 2,400
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $256,587 1,711,214
kWh
Natural Gas $680,244 121,851
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,216 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,074 - n/a $8,074
58,019
kWh
-
02 2.2135: Repair and eliminate steam leaks $3,660 $312 n/a - $3,660
-
MMBtu
03 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $65,362 $60,000 n/a $65,362
435,923
kWh
-
04 2.1242: Minimize boiler blowdown with better feedwater treatment $1,624 $1,887 n/a $1,624
10,834
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $290 $454 n/a $290
1,932
kWh
-
06 2.1243: Use heat from boiler blowdown to preheat boiler feed water $1,847 $3,074 n/a - $1,847
-
MMBtu
07 2.2136: Install / repair insulation on steam lines $13,285 $24,474 n/a - $13,285
-
MMBtu
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,293 $2,800 n/a $1,293
8,625
kWh
-
09 2.7135: Install occupancy sensors $1,230 $3,840 n/a $1,230
8,206
kWh
-
10 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $13,726 $60,000 n/a $13,726
91,544
kWh
-
11 2.7142: Utilize higher efficiency lamps and/or ballasts $7,825 $34,552 n/a $7,825
48,708
kWh
-
TOTAL RECOMMENDED $118,216 $191,393 $99,424
663,791
kWh
$18,792
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs