ITAC Assessment: SF0276
ITAC logo
ITAC Assessment: SF0276
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Optical Broad band and video equipment
NAICS 327215: Glass Product Manufacturing Made of Purchased Glass
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 560
Plant Area 110,000
ft2
Annual Production 30,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $933,669 7,409,600
kWh
Electricity Demand $41,117 13,298
kW-mo/yr
Natural Gas $70,858 9,046
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $147,741 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,352 $565 $2,271
19,002
kWh
$81
-
kW-mo/yr
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $51,751 $27,610 $49,979
418,585
kWh
$1,772
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,158 $18,940 n/a $16,953
144,988
kWh
$1,205
-
kW-mo/yr
-
04 2.2628: Utilize a less expensive cooling method $55,744 $58,875 n/a $53,931
428,363
kWh
$1,813
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $977 $3,120 $863
7,220
kWh
$114
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,720 $14,141 $3,237
27,113
kWh
$483
-
kW-mo/yr
-
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $15,039 $7,370 - - $15,039
-
lb
TOTAL RECOMMENDED $147,741 $130,621 $127,234
1,045,271
kWh
$5,468
-
kW-mo/yr
$15,039
-
lb
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs