Assessment Year | 2004 |
---|---|
Principal Product | Optical Broad band and video equipment |
NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 560 |
Plant Area |
110,000
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $933,669 | 7,409,600 |
kWh
|
$0.13 |
Electricity Demand | $41,117 | 13,298 |
kW-mo/yr
|
$3.09 |
Natural Gas | $70,858 | 9,046 |
MMBtu
|
$7.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $147,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,352 | $565 |
$2,271
19,002
kWh
|
$81
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $51,751 | $27,610 |
$49,979
418,585
kWh
|
$1,772
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,158 | $18,940 | n/a |
$16,953
144,988
kWh
|
$1,205
-
kW-mo/yr
|
- |
04 | 2.2628: Utilize a less expensive cooling method | $55,744 | $58,875 | n/a |
$53,931
428,363
kWh
|
$1,813
-
kW-mo/yr
|
- |
05 | 2.7135: Install occupancy sensors | $977 | $3,120 |
$863
7,220
kWh
|
$114
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,720 | $14,141 |
$3,237
27,113
kWh
|
$483
-
kW-mo/yr
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $15,039 | $7,370 | - | - |
$15,039
-
lb
|
|
TOTAL RECOMMENDED | $147,741 | $130,621 |
$127,234
1,045,271
kWh
|
$5,468
-
kW-mo/yr
|
$15,039
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs