ITAC Assessment: SF0275
ITAC logo
ITAC Assessment: SF0275
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Dairy Product
NAICS 311520: Ice Cream and Frozen Dessert Manufacturing
SIC 2026: Fluid Milk
Sales Range $100
M
to 500
M
# of Employees 100
Plant Area
n/a
Annual Production 18,200,000
Tgal
Production Hrs. Annual 4,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $724,659 9,844,053
kWh
Electricity Demand $143,766 30,237
kW-mo/yr
Natural Gas $1,022,553 85,928
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $96,493 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,709

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.4131: Size electric motors for peak operating efficiency $2,063 $739 $1,548
21,034
kWh
$515
-
kW-mo/yr
- -
02 2.2441: Preheat boiler makeup water with waste process heat $49,562 $39,000 - - $49,562
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $6,238 - $5,602
76,105
kWh
$636
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,909 $3,688 $1,605
21,810
kWh
$304
-
kW-mo/yr
- -
05 2.2514: Cover open tanks $715 $1,469 - - $715
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,604 $12,835 $2,954
40,137
kWh
$650
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $1,197 $4,096 $935
12,705
kWh
$262
-
kW-mo/yr
- -
08 2.7134: Use photocell controls $613 $2,971 $524
7,118
kWh
$89
-
kW-mo/yr
- -
09 2.2612: Use cooling tower water instead of refrigeration $30,592 $34,814 - - - $30,592
-
Tgal
TOTAL RECOMMENDED $96,493 $99,612 $13,168
178,909
kWh
$2,456
-
kW-mo/yr
$50,277
-
MMBtu
$30,592
-
Tgal
TOTAL IMPLEMENTED $57,709 $42,688 $7,207
97,915
kWh
$940
-
kW-mo/yr
$49,562
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs