ITAC Assessment: GT0226
ITAC logo
ITAC Assessment: GT0226
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product PACKAGED ICE
NAICS
n/a
SIC 2097: Manufactured Ice
Sales Range $1
M
to 5
M
# of Employees 13
Plant Area
n/a
Annual Production 20,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,953 451,934
kWh
Natural Gas $2,939 484
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,094 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,244

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2437: Recover waste heat from equipment $7,999 $10,000 - $2,939
-
MMBtu
$5,060
02 2.4133: Use most efficient type of electric motors $245 $104 $245
4,103
kWh
- -
03 2.2444: Use hot process fluids to preheat incoming process fluids $850 $2,300 $850
14,068
kWh
- -
TOTAL RECOMMENDED $9,094 $12,404 $1,095
18,171
kWh
$2,939
-
MMBtu
$5,060
TOTAL IMPLEMENTED $8,244 $10,104 $245
4,103
kWh
$2,939
-
MMBtu
$5,060
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs