Assessment Year | 2003 |
---|---|
Principal Product | Asphalt Roofing Shingles |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $10 M to 50M |
# of Employees | 79 |
Plant Area |
267,800
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,960
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $568,833 | 4,467,600 |
kWh
|
$0.13 |
Electricity Demand | $106,196 | 9,684 |
kW-mo/yr
|
$10.97 |
Natural Gas | $460,999 | 112,442 |
MMBtu
|
$4.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $256,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $92,387 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,393 | $420 |
$7,393
71,642
kWh
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,964 | $567 |
$1,964
19,035
kWh
|
- | - | - | - | |
03 | 2.7134: Use photocell controls | $2,225 | $2,760 |
$1,381
13,380
kWh
|
$844
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,846 | $38,640 |
$20,152
195,270
kWh
|
$3,694
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,167 | $8,360 |
$4,367
42,317
kWh
|
$800
-
kW-mo/yr
|
- | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,193 | $15,000 |
$6,580
63,761
kWh
|
$1,613
-
kW-mo/yr
|
- | - | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $142,307 | $525,000 | - | - |
$142,307
-
MMBtu
|
- | - | |
08 | 3.6192: Use a less expensive method of waste removal | $56,959 | $350 | - | - | - | $56,959 | - | |
09 | 4.131: Modify process to reduce material use/cost | $8,073 | $20,578 | - | - | - | - | $8,073 | |
TOTAL RECOMMENDED | $256,127 | $611,675 |
$41,837
405,405
kWh
|
$6,951
-
kW-mo/yr
|
$142,307
-
MMBtu
|
$56,959 | $8,073 | ||
TOTAL IMPLEMENTED | $92,387 | $42,737 |
$30,890
299,327
kWh
|
$4,538
-
kW-mo/yr
|
- | $56,959 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs