| Assessment Year | 2003 |
|---|---|
| Principal Product | Snack Pies |
| NAICS | 311919: Other Snack Food Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
56,000
ft2
|
| Annual Production | 100,000,000
units
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $220,578 | 1,977,743 |
kWh
|
$0.11 |
| Electricity Demand | $58,258 | 4,472 |
kW-mo/yr
|
$13.03 |
| Natural Gas | $70,779 | 13,033 |
MMBtu
|
$5.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $200,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $1,280 | $960 |
$1,151
10,547
kWh
|
$129
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $2,484 | $1,369 |
$2,051
18,785
kWh
|
$433
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7132: Install timers on light switches in little used areas | $1,765 | $2,200 |
$1,477
13,539
kWh
|
$288
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $4,660 | $7,712 | - | - |
$4,660
-
MMBtu
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,906 | $260 | - | - | - |
$4,906
-
Tgal
|
- | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,400 | $24,250 | - | - | - | - | $5,400 | |
| 07 | 3.2176: Increase use of automation | $179,712 | $500,000 | - | - | - | - | $179,712 | |
| TOTAL RECOMMENDED | $200,207 | $536,751 |
$4,679
42,871
kWh
|
$850
-
kW-mo/yr
|
$4,660
-
MMBtu
|
$4,906
-
Tgal
|
$185,112 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs