| Assessment Year | 2002 |
|---|---|
| Principal Product | Plastic Containers |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
137,500
ft2
|
| Annual Production | 90,000,000
pieces
|
| Production Hrs. Annual | 8,496
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $683,095 | 7,866,300 |
kWh
|
$0.087 |
| Electricity Demand | $154,209 | 13,926 |
kW-mo/yr
|
$11.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $251,681 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $59,274 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,508 | - |
$3,508
41,042
kWh
|
- | - | - | - | |
| 02 | 2.4224: Upgrade controls on compressors | $9,751 | - |
$9,751
95,376
kWh
|
- | - | - | - | |
| 03 | 4.111: Add equipment/ operators to reduce production bottleneck | $11,151 | $1,893 |
$11,151
109,027
kWh
|
- | - | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $595 | $366 |
$595
5,820
kWh
|
- | - | - | - | |
| 05 | 2.7134: Use photocell controls | $5,440 | $3,960 |
$5,440
24,537
kWh
|
- | - | - | - | |
| 06 | 2.2314: Replace heat treating oven with more efficient unit | $50,830 | $54,425 |
$55,182
637,200
kWh
|
$11,956
-
kW-mo/yr
|
- |
$(-16,308.0)
-
MMBtu
|
- | |
| 07 | 2.7132: Install timers on light switches in little used areas | $6,090 | $7,975 |
$6,090
70,327
kWh
|
- | - | - | - | |
| 08 | 2.7132: Install timers on light switches in little used areas | $365 | $750 |
$365
3,568
kWh
|
- | - | - | - | |
| 09 | 2.5123: Reduce fluid flow rates | $3,021 | $7,646 |
$3,021
29,545
kWh
|
- | - | - | - | |
| 10 | 2.2511: Insulate bare equipment | $3,436 | $9,800 |
$3,436
39,671
kWh
|
- | - | - | - | |
| 11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $38,555 | $166,322 |
$38,555
379,136
kWh
|
- | - | - | - | |
| 12 | 4.111: Add equipment/ operators to reduce production bottleneck | $38,019 | $150 | - | - | - | - |
$38,019
-
lb
|
|
| 13 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,560 | $9,550 | - | - | - | - |
$4,560
-
lb
|
|
| 14 | 2.8114: Change rate schedules or other changes in utility service | $76,360 | $160,000 | - | - | $76,360 | - | - | |
| TOTAL RECOMMENDED | $251,681 | $422,837 |
$137,094
1,435,249
kWh
|
$11,956
-
kW-mo/yr
|
$76,360 |
$(-16,308.0)
-
MMBtu
|
$42,579
-
lb
|
||
| TOTAL IMPLEMENTED | $59,274 | $19,500 |
$16,695
176,089
kWh
|
- | - | - |
$42,579
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs