ITAC Assessment: SF0246
ITAC logo
ITAC Assessment: SF0246
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Sauces and Salad Dressings
NAICS
n/a
SIC 2235:
Sales Range $5
M
to 10
M
# of Employees 35
Plant Area 40,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,394 490,640
kWh
Electricity Demand $10,614 2,307
kW-mo/yr
Natural Gas $22,721 3,113
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,350 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,138

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7134: Use photocell controls $800 $240 - $800
-
MMBtu
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $285 $166 $285
1,934
kWh
- - -
03 4.111: Add equipment/ operators to reduce production bottleneck $8,497 $22,500 $8,497
66,224
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $853 $3,180 $853
5,512
kWh
- - -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $16,661 $16,445 - - $16,661
-
lb
-
06 4.448: Install automatic part storage / retreval system $67,254 $7,095 - - - $67,254
TOTAL RECOMMENDED $94,350 $49,626 $9,635
73,670
kWh
$800
-
MMBtu
$16,661
-
lb
$67,254
TOTAL IMPLEMENTED $1,138 $3,346 $1,138
7,446
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs