| Assessment Year | 2002 |
|---|---|
| Principal Product | Sauces and Salad Dressings |
| NAICS |
n/a
|
| SIC | 2235: |
| Sales Range | $5 M to 10M |
| # of Employees | 35 |
| Plant Area |
40,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,394 | 490,640 |
kWh
|
$0.11 |
| Electricity Demand | $10,614 | 2,307 |
kW-mo/yr
|
$4.60 |
| Natural Gas | $22,721 | 3,113 |
MMBtu
|
$7.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $94,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,138 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7134: Use photocell controls | $800 | $240 | - |
$800
-
MMBtu
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $285 | $166 |
$285
1,934
kWh
|
- | - | - | |
| 03 | 4.111: Add equipment/ operators to reduce production bottleneck | $8,497 | $22,500 |
$8,497
66,224
kWh
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $853 | $3,180 |
$853
5,512
kWh
|
- | - | - | |
| 05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $16,661 | $16,445 | - | - |
$16,661
-
lb
|
- | |
| 06 | 4.448: Install automatic part storage / retreval system | $67,254 | $7,095 | - | - | - | $67,254 | |
| TOTAL RECOMMENDED | $94,350 | $49,626 |
$9,635
73,670
kWh
|
$800
-
MMBtu
|
$16,661
-
lb
|
$67,254 | ||
| TOTAL IMPLEMENTED | $1,138 | $3,346 |
$1,138
7,446
kWh
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs