Assessment Year | 2020 |
---|---|
Principal Product | Aluminum beverage cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $100 M to 500M |
# of Employees | 163 |
Plant Area |
350,000
ft2
|
Annual Production | 2,000,000,000
pieces
|
Production Hrs. Annual | 8,688
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,460,363 | 45,636,370 |
kWh
|
$0.032 | |
Electricity Demand | $880,560 | 90,967 |
kW-mo/yr
|
$9.68 | |
Electricity Fees | $160,182 | - |
|
- | |
Natural Gas | $380,043 | 106,305 |
MMBtu
|
$3.58 | |
Waste Disposal Costs | |||||
Water Usage | $35 | 5 |
Tgal
|
$7.00 | |
TOTAL YEARLY COSTS | $2,881,183 | ||||
RECOMMENDED SAVINGS* | $579,660 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $535,860 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $336,600 | - | - | - | $168,300 | $168,300 | |
02 | 2.3212: Optimize plant power factor | $126,730 | $229,415 | - |
$126,730
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $66,000 | $20,000 |
$44,080
1,377,000
kWh
|
$21,920
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $31,045 | $150 |
$20,735
648,000
kWh
|
$10,310
-
kW-mo/yr
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10,800 | $4,680 |
$7,200
226,000
kWh
|
$3,600
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,120 | $11,560 |
$3,420
107,000
kWh
|
$1,700
-
kW-mo/yr
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $1,955 | - | - |
$1,955
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,410 | $1,570 |
$710
22,130
kWh
|
$700
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $579,660 | $267,375 |
$76,145
2,380,130
kWh
|
$166,915
-
kW-mo/yr
|
$168,300 | $168,300 | ||
TOTAL IMPLEMENTED | $535,860 | $262,545 |
$48,210
1,506,130
kWh
|
$151,050
-
kW-mo/yr
|
$168,300 | $168,300 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs