| Assessment Year | 2002 |
|---|---|
| Principal Product | Toyota Auto Parts |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $1 M to 5M |
| # of Employees | 100 |
| Plant Area |
50,000
ft2
|
| Annual Production | 5,900,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $307,031 | 2,320,897 |
kWh
|
$0.13 |
| Electricity Demand | $43,486 | 9,075 |
kW-mo/yr
|
$4.79 |
| Natural Gas | $21,906 | 3,757 |
MMBtu
|
$5.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,955 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,336 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,642 | $300 |
$1,218
9,211
kWh
|
$424
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,176 | $572 |
$1,084
14,726
kWh
|
$92
-
kW-mo/yr
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,518 | $1,217 |
$2,329
17,633
kWh
|
$189
-
kW-mo/yr
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $4,397 | $3,036 |
$3,973
26,874
kWh
|
$424
-
kW-mo/yr
|
- | - | |
| 05 | 2.4234: Cool compressor air intake with heat exchanger | $553 | $1,000 |
$441
3,337
kWh
|
$112
-
kW-mo/yr
|
- | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $2,020 | $3,067 | - | - |
$2,020
-
MMBtu
|
- | |
| 07 | 2.7134: Use photocell controls | $433 | $1,200 |
$399
3,020
kWh
|
$34
-
kW-mo/yr
|
- | - | |
| 08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $16,216 | $16,216 | - | - | - |
$16,216
-
lb
|
|
| TOTAL RECOMMENDED | $28,955 | $26,608 |
$9,444
74,801
kWh
|
$1,275
-
kW-mo/yr
|
$2,020
-
MMBtu
|
$16,216
-
lb
|
||
| TOTAL IMPLEMENTED | $5,336 | $2,089 |
$4,631
41,570
kWh
|
$705
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs