Assessment Year | 2002 |
---|---|
Principal Product | Metal Products |
NAICS |
n/a
|
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
81,460
ft2
|
Annual Production | 1,385
ton
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $416,011 | 3,501,220 |
kWh
|
$0.12 |
Natural Gas | $111,163 | 10,313 |
MMBtu
|
$10.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $63,010 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,626 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,185 | $300 |
$7,185
31,959
kWh
|
- | |
02 | 2.7134: Use photocell controls | $8,489 | $6,960 |
$8,489
52,595
kWh
|
- | |
03 | 2.7132: Install timers on light switches in little used areas | $988 | $1,250 |
$988
3,745
kWh
|
- | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $904 | $1,304 | - | $904 | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,974 | $10,307 |
$4,974
28,587
kWh
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,310 | $14,027 |
$6,310
31,750
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,719 | $46,531 |
$18,719
108,958
kWh
|
- | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $15,441 | $49,000 |
$15,441
(-79,719)
kWh
|
- | |
TOTAL RECOMMENDED | $63,010 | $129,679 |
$62,106
177,875
kWh
|
$904 | ||
TOTAL IMPLEMENTED | $22,626 | $49,300 |
$22,626
(-47,760)
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs