ITAC Assessment: SF0206
ITAC logo
ITAC Assessment: SF0206
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Custom Injection Molding
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 20,000
ft2
Annual Production 40,000,000
units
Production Hrs. Annual 7,248
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,499 1,373,524
kWh
Natural Gas $332 27
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,917 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,728

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings
01 2.2625: Chill water to the highest temperature possible $2,884 $475 $2,884
31,175
kWh
-
02 2.4133: Use most efficient type of electric motors $7,007 $7,832 $7,007
75,748
kWh
-
03 2.7132: Install timers on light switches in little used areas $2,881 $2,910 $2,881
31,138
kWh
-
04 2.7135: Install occupancy sensors $668 $600 $668
7,222
kWh
-
05 2.7132: Install timers on light switches in little used areas $332 $500 $332
3,591
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,381 $24,410 $8,381
96,546
kWh
-
07 2.7135: Install occupancy sensors $4,060 $22,250 $4,060
43,890
kWh
-
08 3.6111: Use alternative flocculent to minimize sludge volume $6,704 $19,400 - $6,704
-
lb
TOTAL RECOMMENDED $32,917 $78,377 $26,213
289,310
kWh
$6,704
-
lb
TOTAL IMPLEMENTED $4,728 $22,850 $4,728
51,112
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs