| Assessment Year | 2001 |
|---|---|
| Principal Product | Custom Injection Molding |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 70 |
| Plant Area |
20,000
ft2
|
| Annual Production | 40,000,000
units
|
| Production Hrs. Annual | 7,248
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $137,499 | 1,373,524 |
kWh
|
$0.10 |
| Natural Gas | $332 | 27 |
MMBtu
|
$12.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,917 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,728 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2625: Chill water to the highest temperature possible | $2,884 | $475 |
$2,884
31,175
kWh
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $7,007 | $7,832 |
$7,007
75,748
kWh
|
- | |
| 03 | 2.7132: Install timers on light switches in little used areas | $2,881 | $2,910 |
$2,881
31,138
kWh
|
- | |
| 04 | 2.7135: Install occupancy sensors | $668 | $600 |
$668
7,222
kWh
|
- | |
| 05 | 2.7132: Install timers on light switches in little used areas | $332 | $500 |
$332
3,591
kWh
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,381 | $24,410 |
$8,381
96,546
kWh
|
- | |
| 07 | 2.7135: Install occupancy sensors | $4,060 | $22,250 |
$4,060
43,890
kWh
|
- | |
| 08 | 3.6111: Use alternative flocculent to minimize sludge volume | $6,704 | $19,400 | - |
$6,704
-
lb
|
|
| TOTAL RECOMMENDED | $32,917 | $78,377 |
$26,213
289,310
kWh
|
$6,704
-
lb
|
||
| TOTAL IMPLEMENTED | $4,728 | $22,850 |
$4,728
51,112
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs