| Assessment Year | 2000 |
|---|---|
| Principal Product | Wallboard |
| NAICS |
n/a
|
| SIC | 3275: Gypsum Products |
| Sales Range | $10 M to 50M |
| # of Employees | 54 |
| Plant Area |
200,000
ft2
|
| Annual Production | 230,000,000
thousand feet
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $687,851 | 10,200,668 |
kWh
|
$0.067 |
| Natural Gas | $1,777,271 | 589,091 |
MMBtu
|
$3.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $94,810 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $47,536 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 3.7392: Apply a protective coating to racks and tanks | $4,646 | $120 |
$4,646
69,131
kWh
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,708 | $25 |
$1,708
25,417
kWh
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $23,492 | $19,738 |
$23,492
349,548
kWh
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $15,456 | $15,452 |
$15,456
229,964
kWh
|
- | |
| 05 | 2.7132: Install timers on light switches in little used areas | $7,180 | $11,750 |
$7,180
106,814
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,796 | $8,825 |
$3,796
56,486
kWh
|
- | |
| 07 | 3.5311: Recover and reuse waste material | $12,259 | $7,650 | - |
$12,259
-
lb
|
|
| 08 | 3.5311: Recover and reuse waste material | $1,635 | - | - |
$1,635
-
lb
|
|
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $24,638 | $18,750 | - |
$24,638
-
lb
|
|
| TOTAL RECOMMENDED | $94,810 | $82,310 |
$56,278
837,360
kWh
|
$38,532
-
lb
|
||
| TOTAL IMPLEMENTED | $47,536 | $36,358 |
$33,642
500,582
kWh
|
$13,894
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs