Assessment Year | 2000 |
---|---|
Principal Product | Transformers |
NAICS |
n/a
|
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
135,000
ft2
|
Annual Production | 80
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,905 | 2,589,818 |
kWh
|
$0.057 |
Electricity Demand | $98,443 | 10,866 |
kW-mo/yr
|
$9.06 |
Natural Gas | $25,050 | 4,278 |
MMBtu
|
$5.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,703 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,056 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,221 | - |
$1,221
21,093
kWh
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,327 | $2,998 |
$1,327
22,922
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,017 | $14,420 |
$4,017
69,381
kWh
|
- | - | |
04 | 2.7135: Install occupancy sensors | $1,208 | $4,500 |
$1,208
20,861
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $488 | $2,166 |
$488
8,450
kWh
|
- | - | |
06 | 3.5313: Increase amount of waste recovered for resale | $1,818 | - | - |
$1,818
-
lb
|
- | |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $848 | - | - |
$848
-
lb
|
- | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $15,600 | $89,000 | - |
$15,600
-
lb
|
- | |
09 | 2.2314: Replace heat treating oven with more efficient unit | $27,526 | $28,000 |
$27,526
475,200
kWh
|
- | - | |
10 | 4.711: Initiate a total quality management program | $27,650 | $130,000 | - | - | $27,650 | |
TOTAL RECOMMENDED | $81,703 | $271,084 |
$35,787
617,907
kWh
|
$18,266
-
lb
|
$27,650 | ||
TOTAL IMPLEMENTED | $7,056 | $14,420 |
$5,238
90,474
kWh
|
$1,818
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs