Assessment Year | 2000 |
---|---|
Principal Product | Salty Snacks |
NAICS |
n/a
|
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
124,000
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 5,330
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $354,465 | 3,523,680 |
kWh
|
$0.10 |
Electricity Demand | $106,036 | 8,823 |
kW-mo/yr
|
$12.02 |
Natural Gas | $408,752 | 111,959 |
MMBtu
|
$3.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $152,796 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,959 | - |
$1,319
21,981
kWh
|
$640
-
kW-mo/yr
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $2,262 | $840 |
$1,522
25,205
kWh
|
$740
-
kW-mo/yr
|
- | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $7,576 | $5,200 |
$5,098
84,701
kWh
|
$2,478
-
kW-mo/yr
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $1,075 | $956 | - | - |
$1,075
-
MMBtu
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,881 | $2,455 |
$1,266
21,102
kWh
|
$615
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,009 | $10,260 |
$4,578
76,202
kWh
|
$2,431
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,128 | $6,420 |
$1,685
20,809
kWh
|
$443
-
kW-mo/yr
|
- | - | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $21,696 | $850 |
$(-144.0)
(-2,345)
kWh
|
- | - | - | $21,840 | |
09 | 4.131: Modify process to reduce material use/cost | $63,815 | $35,960 | - | - | - |
$4,119
-
lb
|
$59,696 | |
10 | 4.711: Initiate a total quality management program | $43,395 | $130,000 | - | - | - | - | $43,395 | |
TOTAL RECOMMENDED | $152,796 | $192,941 |
$15,324
247,655
kWh
|
$7,347
-
kW-mo/yr
|
$1,075
-
MMBtu
|
$4,119
-
lb
|
$124,931 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs