| Assessment Year | 2000 |
|---|---|
| Principal Product | Printing Plates and Dies |
| NAICS |
n/a
|
| SIC | 2796: Platemaking and Related Services |
| Sales Range | $5 M to 10M |
| # of Employees | 80 |
| Plant Area |
36,000
ft2
|
| Annual Production | 11,000
thousand feet
|
| Production Hrs. Annual | 6,656
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $38,894 | 838,804 |
kWh
|
$0.046 |
| Electricity Demand | $12,786 | 2,046 |
kW-mo/yr
|
$6.25 |
| Natural Gas | $329 | 28 |
MMBtu
|
$11.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,590 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $761 | $720 |
$592
12,896
kWh
|
$169
-
kW-mo/yr
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,990 | $3,103 |
$3,010
64,771
kWh
|
$557
-
kW-mo/yr
|
$(-1,577.0)
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,492 | $15,620 |
$6,599
142,438
kWh
|
$1,893
-
kW-mo/yr
|
- | - | |
| 04 | 3.5313: Increase amount of waste recovered for resale | $838 | - | - | - | - |
$838
-
lb
|
|
| 05 | 3.5313: Increase amount of waste recovered for resale | $509 | - | - | - | - |
$509
-
lb
|
|
| TOTAL RECOMMENDED | $12,590 | $19,443 |
$10,201
220,105
kWh
|
$2,619
-
kW-mo/yr
|
$(-1,577.0)
-
MMBtu
|
$1,347
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs