ITAC Assessment: SF0179
ITAC logo
ITAC Assessment: SF0179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Nutritional Suplements
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area 17,000
ft2
Annual Production 1,300,000
pieces
Production Hrs. Annual 2,730
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,552 227,726
kWh
Electricity Demand $4,000 717
kW-mo/yr
Natural Gas $6,152 985
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $71,514 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,310

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7135: Install occupancy sensors $276 $480 $206
2,931
kWh
$70
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,662 $6,782 $2,065
28,429
kWh
$597
-
kW-mo/yr
- -
03 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $564 $2,476 $564
7,913
kWh
- - -
04 3.5248: Separate and recycle scrap metal to foundry or for sale $1,350 $150 - - $1,350
-
lb
-
05 3.5313: Increase amount of waste recovered for resale $600 $150 - - $600
-
lb
-
06 3.5315: Lease / purchase baler; sell cardboard to recycler $312 $150 - - $312
-
lb
-
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $6,334 $8,650 - - $6,334
-
lb
-
08 4.652: Replace existing equipment with more suitable substitutes $7,000 $838 - - - $7,000
09 4.445: Install equipment to move product $26,208 $33,300 - - - $26,208
10 4.445: Install equipment to move product $26,208 $33,300 - - - $26,208
TOTAL RECOMMENDED $71,514 $86,276 $2,835
39,273
kWh
$667
-
kW-mo/yr
$8,596
-
lb
$59,416
TOTAL IMPLEMENTED $36,310 $37,544 $770
10,844
kWh
$70
-
kW-mo/yr
$2,262
-
lb
$33,208
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs