Assessment Year | 1999 |
---|---|
Principal Product | Semiconductor Etching Equipment |
NAICS |
n/a
|
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 140 |
Plant Area |
120,000
ft2
|
Annual Production | 84
pieces
|
Production Hrs. Annual | 2,830
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $312,079 | 5,917,351 |
kWh
|
$0.053 |
Electricity Demand | $140,002 | 10,342 |
kW-mo/yr
|
$13.54 |
Natural Gas | $35,530 | 6,695 |
MMBtu
|
$5.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $301,357 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $228,527 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $954 | - |
$954
18,171
kWh
|
- | - | - | |
02 | 2.7226: Use computer programs to optimize hvac performance | $88,107 | $21,913 |
$82,190
1,559,789
kWh
|
$5,917
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $2,195 | $2,425 |
$1,597
30,188
kWh
|
$598
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $29,353 | $51,620 |
$19,491
369,871
kWh
|
$9,862
-
kW-mo/yr
|
- | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $8,353 | $18,000 |
$8,353
158,558
kWh
|
- | - | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $818 | - | - | - |
$818
-
lb
|
- | |
07 | 4.521: Clear and rent existing space | $107,100 | $6,400 | - | - | - | $107,100 | |
08 | 2.8114: Change rate schedules or other changes in utility service | $61,603 | $115,000 | - | - | - | $61,603 | |
09 | 2.3212: Optimize plant power factor | $2,874 | $5,535 | - | - | - | $2,874 | |
TOTAL RECOMMENDED | $301,357 | $220,893 |
$112,585
2,136,577
kWh
|
$16,377
-
kW-mo/yr
|
$818
-
lb
|
$171,577 | ||
TOTAL IMPLEMENTED | $228,527 | $82,358 |
$104,232
1,978,019
kWh
|
$16,377
-
kW-mo/yr
|
$818
-
lb
|
$107,100 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs