Assessment Year | 1999 |
---|---|
Principal Product | Bakers Yeast |
NAICS |
n/a
|
SIC | 2053: Frozen Bakery Products, Except Bread |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
132,000
ft2
|
Annual Production | 70,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $741,045 | 15,072,099 |
kWh
|
$0.049 |
Electricity Demand | $372,828 | 34,521 |
kW-mo/yr
|
$10.80 |
Natural Gas | $264,498 | 88,625 |
MMBtu
|
$2.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $436,558 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $226,916 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $7,540 | - | - | - |
$7,540
-
MMBtu
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,924 | $1,958 |
$5,003
101,700
kWh
|
$1,921
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $1,121 | $825 | - | - |
$1,121
-
MMBtu
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $2,054 | $1,800 |
$1,434
29,015
kWh
|
$620
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,100 | $15,856 |
$10,416
205,158
kWh
|
$1,684
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $124,530 | $236,733 |
$89,957
1,829,719
kWh
|
$34,573
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $4,368 | $7,209 |
$3,156
64,185
kWh
|
$1,212
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,548 | $14,600 |
$4,010
81,477
kWh
|
$2,538
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2437: Recover waste heat from equipment | $8,448 | $21,777 | - | - |
$8,448
-
MMBtu
|
- | - | - | |
10 | 2.7134: Use photocell controls | $5,543 | $21,500 |
$4,005
81,477
kWh
|
$1,538
-
kW-mo/yr
|
- | - | - | - | |
11 | 3.5314: Use in-process recycling whenever possible | $960 | - | - | - | - | - |
$960
-
lb
|
- | |
12 | 3.5313: Increase amount of waste recovered for resale | $10,400 | - | - | - | - | - |
$10,400
-
lb
|
- | |
13 | 3.5316: Contract a wood pallet recycling company | $1,632 | $250 | - | - | - | - |
$1,632
-
lb
|
- | |
14 | 2.8122: Use utility controlled power management | $138,720 | $11,500 | - | - | - | - | - | $138,720 | |
15 | 2.8122: Use utility controlled power management | $1,726 | - | - | - | - | - | - | $1,726 | |
16 | 2.8122: Use utility controlled power management | $44,655 | $23,000 | - | - | - | - | - | $44,655 | |
17 | 2.3212: Optimize plant power factor | $3,752 | $9,602 | - | - | - | - | - | $3,752 | |
18 | 3.4116: Meter recycled water (to reduce sewer charges) | $55,537 | $10,830 | - | - | - |
$55,537
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $436,558 | $377,440 |
$117,981
2,392,731
kWh
|
$44,086
-
kW-mo/yr
|
$17,109
-
MMBtu
|
$55,537
-
Tgal
|
$12,992
-
lb
|
$188,853 | ||
TOTAL IMPLEMENTED | $226,916 | $68,069 |
$9,593
194,900
kWh
|
$3,753
-
kW-mo/yr
|
$17,109
-
MMBtu
|
- |
$11,360
-
lb
|
$185,101 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs