| Assessment Year | 1999 |
|---|---|
| Principal Product | Injection Molded Plastic Parts |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
25,000
ft2
|
| Annual Production | 1,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $89,811 | 1,503,224 |
kWh
|
$0.060 |
| Electricity Demand | $42,460 | 3,886 |
kW-mo/yr
|
$10.93 |
| Natural Gas | $1,830 | 238 |
MMBtu
|
$7.69 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,237 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $535 | $889 | n/a |
$395
6,741
kWh
|
$140
-
kW-mo/yr
|
- | - |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,152 | $14,840 | n/a |
$5,043
84,408
kWh
|
$2,109
-
kW-mo/yr
|
- | - |
| 03 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $491 | $1,250 | n/a |
$239
4,103
kWh
|
$252
-
kW-mo/yr
|
- | - |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,333 | $51,850 | n/a |
$9,623
161,196
kWh
|
$2,710
-
kW-mo/yr
|
- | - |
| 05 | 3.5314: Use in-process recycling whenever possible | $726 | - | n/a | - | - |
$726
-
lb
|
- |
| 06 | 4.445: Install equipment to move product | $30,000 | $2,773 | n/a | - | - | - | $30,000 |
| TOTAL RECOMMENDED | $51,237 | $71,602 |
$15,300
256,448
kWh
|
$5,211
-
kW-mo/yr
|
$726
-
lb
|
$30,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs