| Assessment Year | 1997 |
|---|---|
| Principal Product | Brooms,Mops,and Handles |
| NAICS |
n/a
|
| SIC | 3991: Brooms and Brushes |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
40,000
ft2
|
| Annual Production | 400,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $9,923 | 122,509 |
kWh
|
$0.081 |
| Electricity Demand | $1,990 | 598 |
kW-mo/yr
|
$3.33 |
| Natural Gas | $7,209 | 1,191 |
MMBtu
|
$6.05 |
| LPG | $8,393 | 733 |
MMBtu
|
$11.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,093 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,043 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1332: Convert combustion equipment to burn natural gas | $3,157 | $602 | - | - |
$(-3,908.0)
-
MMBtu
|
$7,065
-
MMBtu
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $777 | $2,520 |
$593
7,327
kWh
|
$184
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.2511: Insulate bare equipment | $267 | $300 |
$267
12,896
kWh
|
- | - | - | - | - | |
| 04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $9,592 | $250 | - | - | - | - |
$9,592
-
lb
|
- | |
| 05 | 4.112: Replace old machine with new automatic multi-station tool | $2,250 | $2,000 | - | - | - | - | - | $2,250 | |
| 06 | 4.441: Install automatic packing equipment | $2,050 | $5,150 | - | - | - | - | - | $2,050 | |
| TOTAL RECOMMENDED | $18,093 | $10,822 |
$860
20,223
kWh
|
$184
-
kW-mo/yr
|
$(-3,908.0)
-
MMBtu
|
$7,065
-
MMBtu
|
$9,592
-
lb
|
$4,300 | ||
| TOTAL IMPLEMENTED | $16,043 | $5,672 |
$860
20,223
kWh
|
$184
-
kW-mo/yr
|
$(-3,908.0)
-
MMBtu
|
$7,065
-
MMBtu
|
$9,592
-
lb
|
$2,250 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs