ITAC Assessment: SF0128
ITAC logo
ITAC Assessment: SF0128
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Exhibits
NAICS
n/a
SIC 2599: Furniture and Fixtures, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 280,000
ft2
Annual Production 300
pieces
Production Hrs. Annual 2,600
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,553 1,027,257
kWh
Electricity Demand $13,345 3,380
kW-mo/yr
Natural Gas $10,408 1,808
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,832 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,021

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $500 $742 $403
4,982
kWh
$97
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $1,849 $3,760 $1,669
20,516
kWh
$180
-
kW-mo/yr
-
03 2.7131: Add area lighting switches $535 $850 $431
5,275
kWh
$104
-
kW-mo/yr
-
04 2.7134: Use photocell controls $1,929 $1,500 $1,556
19,050
kWh
$373
-
kW-mo/yr
-
05 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $970 $1,500 $783
9,672
kWh
$187
-
kW-mo/yr
-
06 2.7144: Install spectral reflectors / delamp $5,094 $8,069 $4,547
55,979
kWh
$547
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $434 $1,440 $350
4,396
kWh
$84
-
kW-mo/yr
-
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,081 $12,944 $5,081
62,427
kWh
- -
09 2.4231: Reduce the pressure of compressed air to the minimum required $253 $25 $204
2,638
kWh
$49
-
kW-mo/yr
-
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $521 $300 $420
5,275
kWh
$101
-
kW-mo/yr
-
11 3.5313: Increase amount of waste recovered for resale $630 $195 - - $630
-
lb
12 3.5315: Lease / purchase baler; sell cardboard to recycler $36 - - - $36
-
lb
TOTAL RECOMMENDED $17,832 $31,325 $15,444
190,210
kWh
$1,722
-
kW-mo/yr
$666
-
lb
TOTAL IMPLEMENTED $7,021 $14,206 $6,108
75,322
kWh
$247
-
kW-mo/yr
$666
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs