Assessment Year | 1997 |
---|---|
Principal Product | Babbitt Bearings |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 45 |
Plant Area |
25,000
ft2
|
Annual Production | 1,400
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $17,985 | 222,157 |
kWh
|
$0.081 |
Electricity Demand | $4,390 | 1,048 |
kW-mo/yr
|
$4.19 |
Natural Gas | $14,396 | 2,688 |
MMBtu
|
$5.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,676 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,676 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7134: Use photocell controls | $1,069 | $1,500 |
$864
10,551
kWh
|
$205
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,307 | - |
$1,248
14,947
kWh
|
$59
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $790 | $60 |
$638
7,913
kWh
|
$152
-
kW-mo/yr
|
- | |
04 | 2.6218: Turn off equipment when not in use | $1,633 | - |
$1,257
15,533
kWh
|
$376
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $143 | $720 |
$143
1,758
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $1,656 | $2,000 |
$1,656
90,563
kWh
|
- | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $78 | $120 | - | - |
$78
-
lb
|
|
TOTAL RECOMMENDED | $6,676 | $4,400 |
$5,806
141,265
kWh
|
$792
-
kW-mo/yr
|
$78
-
lb
|
||
TOTAL IMPLEMENTED | $6,676 | $4,400 |
$5,806
141,265
kWh
|
$792
-
kW-mo/yr
|
$78
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs