ITAC Assessment: SF0121
ITAC logo
ITAC Assessment: SF0121
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Babbitt Bearings
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 25,000
ft2
Annual Production 1,400
pieces
Production Hrs. Annual 2,600
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $17,985 222,157
kWh
Electricity Demand $4,390 1,048
kW-mo/yr
Natural Gas $14,396 2,688
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,676 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,676

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.7134: Use photocell controls $1,069 $1,500 $864
10,551
kWh
$205
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,307 - $1,248
14,947
kWh
$59
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $790 $60 $638
7,913
kWh
$152
-
kW-mo/yr
-
04 2.6218: Turn off equipment when not in use $1,633 - $1,257
15,533
kWh
$376
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $143 $720 $143
1,758
kWh
- -
06 2.2511: Insulate bare equipment $1,656 $2,000 $1,656
90,563
kWh
- -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $78 $120 - - $78
-
lb
TOTAL RECOMMENDED $6,676 $4,400 $5,806
141,265
kWh
$792
-
kW-mo/yr
$78
-
lb
TOTAL IMPLEMENTED $6,676 $4,400 $5,806
141,265
kWh
$792
-
kW-mo/yr
$78
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs