ITAC Assessment: SF0116
ITAC logo
ITAC Assessment: SF0116
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Bread, Cake, and Related Products
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 21,000
ft2
Annual Production 15,400,000
pieces
Production Hrs. Annual 6,916
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,369 789,273
kWh
Electricity Demand $21,243 1,793
kW-mo/yr
Natural Gas $30,000 5,398
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,563 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,027

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $682 $1,560 $502
8,792
kWh
$180
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $361 $467 $266
4,689
kWh
$95
-
kW-mo/yr
-
03 2.3132: Recharge batteries on during off-peak demand periods $190 - - - $190
04 2.7135: Install occupancy sensors $175 $240 $122
2,052
kWh
$53
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $155 $150 $155
2,638
kWh
- -
TOTAL RECOMMENDED $1,563 $2,417 $1,045
18,171
kWh
$328
-
kW-mo/yr
$190
TOTAL IMPLEMENTED $1,027 $1,710 $657
11,430
kWh
$180
-
kW-mo/yr
$190
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs