Assessment Year | 1997 |
---|---|
Principal Product | Printed Polyethylene Film and Bags |
NAICS |
n/a
|
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
43,000
ft2
|
Annual Production | 11,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $248,099 | 5,297,480 |
kWh
|
$0.047 |
Electricity Demand | $88,610 | 6,919 |
kW-mo/yr
|
$12.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,372 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,247 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $18,927 | $31,800 |
$14,141
224,795
kWh
|
$4,786
-
kW-mo/yr
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $3,461 | $1,110 |
$1,078
17,292
kWh
|
$2,383
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,760 | $1,377 |
$8,016
127,491
kWh
|
$2,744
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,526 | $6,600 |
$3,790
60,375
kWh
|
$1,736
-
kW-mo/yr
|
- | |
05 | 2.1213: Direct warmest air to combustion intake | $912 | $2,750 |
$912
44,549
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $686 | $481 |
$536
8,499
kWh
|
$150
-
kW-mo/yr
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $538 | - |
$529
10,258
kWh
|
$9
-
kW-mo/yr
|
- | |
08 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $2,562 | $200 | - | - |
$2,562
-
lb
|
|
TOTAL RECOMMENDED | $43,372 | $44,318 |
$29,002
493,259
kWh
|
$11,808
-
kW-mo/yr
|
$2,562
-
lb
|
||
TOTAL IMPLEMENTED | $7,247 | $1,791 |
$2,143
36,049
kWh
|
$2,542
-
kW-mo/yr
|
$2,562
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs