| Assessment Year | 1996 |
|---|---|
| Principal Product | Plastic Check Valves, Pumps |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 16 |
| Plant Area |
10,500
ft2
|
| Annual Production | 7,300,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $14,581 | 138,335 |
kWh
|
$0.11 |
| Electricity Demand | $1,541 | 492 |
kW-mo/yr
|
$3.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,555 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,241 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $856 | $3,000 |
$1,191
11,137
kWh
|
$162
-
kW-mo/yr
|
$(-497.0)
-
MMBtu
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $905 | $1,082 |
$1,179
10,844
kWh
|
$68
-
kW-mo/yr
|
$(-342.0)
-
MMBtu
|
- | |
| 03 | 2.7135: Install occupancy sensors | $532 | $1,560 |
$475
4,396
kWh
|
$57
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,020 | $5,900 |
$1,733
16,413
kWh
|
$287
-
kW-mo/yr
|
- | - | |
| 05 | 2.6218: Turn off equipment when not in use | $1,782 | $1,960 |
$1,686
16,120
kWh
|
$96
-
kW-mo/yr
|
- | - | |
| 06 | 2.6218: Turn off equipment when not in use | $651 | $600 |
$616
5,862
kWh
|
$35
-
kW-mo/yr
|
- | - | |
| 07 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $809 | $250 | - | - | - |
$809
-
lb
|
|
| TOTAL RECOMMENDED | $7,555 | $14,352 |
$6,880
64,772
kWh
|
$705
-
kW-mo/yr
|
$(-839.0)
-
MMBtu
|
$809
-
lb
|
||
| TOTAL IMPLEMENTED | $5,241 | $10,832 |
$4,719
44,256
kWh
|
$552
-
kW-mo/yr
|
$(-839.0)
-
MMBtu
|
$809
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs