ITAC Assessment: SF0102
ITAC logo
ITAC Assessment: SF0102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Injection Molding pieces
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 20,000
ft2
Annual Production 2,500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,396 397,421
kWh
Electricity Demand $10,604 2,055
kW-mo/yr
Natural Gas $247 15
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,287 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $607

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
01 2.6218: Turn off equipment when not in use $1,138 - $942
13,482
kWh
$196
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,562 $5,950 $1,161
16,706
kWh
$401
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $980 $1,804 $980
14,068
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $261 $50 $228
3,224
kWh
$33
-
kW-mo/yr
-
05 3.4154: Eliminate leaks in water lines and valves $346 $308 - - $346
-
Tgal
TOTAL RECOMMENDED $4,287 $8,112 $3,311
47,480
kWh
$630
-
kW-mo/yr
$346
-
Tgal
TOTAL IMPLEMENTED $607 $358 $228
3,224
kWh
$33
-
kW-mo/yr
$346
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs