| Assessment Year | 1996 |
|---|---|
| Principal Product | Wiring Devices |
| NAICS |
n/a
|
| SIC | 3643: Current-Carrying Wiring Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
60,000
ft2
|
| Annual Production | 150,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $87,777 | 995,897 |
kWh
|
$0.088 |
| Electricity Demand | $15,138 | 3,498 |
kW-mo/yr
|
$4.33 |
| Natural Gas | $2,179 | 317 |
MMBtu
|
$6.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,849 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $583 | $775 |
$522
5,862
kWh
|
$61
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,328 | $3,864 |
$1,117
12,603
kWh
|
$211
-
kW-mo/yr
|
- | |
| 03 | 2.2511: Insulate bare equipment | $1,052 | $5,972 |
$1,052
11,723
kWh
|
- | - | |
| 04 | 2.6218: Turn off equipment when not in use | $1,077 | $1,530 |
$1,052
11,723
kWh
|
$25
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,542 | - |
$1,430
20,223
kWh
|
$112
-
kW-mo/yr
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $722 | $2,520 |
$607
6,741
kWh
|
$115
-
kW-mo/yr
|
- | |
| 07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,255 | $250 | - | - |
$3,255
-
lb
|
|
| TOTAL RECOMMENDED | $9,559 | $14,911 |
$5,780
68,875
kWh
|
$524
-
kW-mo/yr
|
$3,255
-
lb
|
||
| TOTAL IMPLEMENTED | $5,849 | $6,222 |
$2,482
31,946
kWh
|
$112
-
kW-mo/yr
|
$3,255
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs