ITAC Assessment: SF0095
ITAC logo
ITAC Assessment: SF0095
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Stainless Steel Gas Panel Tubing Assemblies
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 47,000
ft2
Annual Production 720,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $179,954 1,939,332
kWh
Electricity Demand $12,832 2,969
kW-mo/yr
Natural Gas $1,561 192
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,561 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $17,141 $19,207 $17,141
140,094
kWh
- - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $9,293 $6,804 $16,188
132,474
kWh
- $(-6,895.0)
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $725 $595 $712
6,741
kWh
$13
-
kW-mo/yr
- -
04 2.6218: Turn off equipment when not in use $3,216 $2,840 $3,216
26,377
kWh
- - -
05 2.7144: Install spectral reflectors / delamp $3,017 $6,950 $2,868
25,791
kWh
$149
-
kW-mo/yr
- -
06 2.2514: Cover open tanks $10,274 $1,400 $10,274
84,115
kWh
- - -
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $6,895 $6,395 - - - $6,895
-
lb
TOTAL RECOMMENDED $50,561 $44,191 $50,399
415,592
kWh
$162
-
kW-mo/yr
$(-6,895.0)
-
MMBtu
$6,895
-
lb
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs