Assessment Year | 1996 |
---|---|
Principal Product | Frozen Bakery Dough |
NAICS |
n/a
|
SIC | 2053: Frozen Bakery Products, Except Bread |
Sales Range | $5 M to 10M |
# of Employees | 98 |
Plant Area |
37,000
ft2
|
Annual Production | 22,500,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,237 | 2,420,574 |
kWh
|
$0.062 |
Electricity Demand | $55,285 | 6,242 |
kW-mo/yr
|
$8.86 |
Natural Gas | $27,906 | 4,784 |
MMBtu
|
$5.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,260 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $659 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,575 | $1,150 |
$1,102
17,585
kWh
|
$473
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,181 | $3,900 |
$731
11,723
kWh
|
$450
-
kW-mo/yr
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $572 | $563 |
$354
5,569
kWh
|
$218
-
kW-mo/yr
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $659 | $962 |
$292
4,689
kWh
|
$478
-
kW-mo/yr
|
$(-111.0)
-
MMBtu
|
- | |
05 | 2.4134: Replace electric motor with fossil fuel engine | $9,436 | $129,300 |
$68,913
1,201,055
kWh
|
$1,994
-
kW-mo/yr
|
$(-61,471.0)
-
MMBtu
|
- | |
06 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $53,507 | $524,531 |
$112,449
1,959,848
kWh
|
$4,622
-
kW-mo/yr
|
$(-63,564.0)
-
MMBtu
|
- | |
07 | 3.5313: Increase amount of waste recovered for resale | $8,330 | $500 | - | - | - |
$8,330
-
lb
|
|
TOTAL RECOMMENDED | $75,260 | $660,906 |
$183,841
3,200,469
kWh
|
$8,235
-
kW-mo/yr
|
$(-125,146.0)
-
MMBtu
|
$8,330
-
lb
|
||
TOTAL IMPLEMENTED | $659 | $962 |
$292
4,689
kWh
|
$478
-
kW-mo/yr
|
$(-111.0)
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs