Assessment Year | 1996 |
---|---|
Principal Product | Sausage and Roast Beef |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $10 M to 50M |
# of Employees | 46 |
Plant Area |
20,000
ft2
|
Annual Production | 4,600,000
lb
|
Production Hrs. Annual | 5,720
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $122,735 | 1,360,785 |
kWh
|
$0.090 |
Electricity Demand | $16,530 | 3,802 |
kW-mo/yr
|
$4.35 |
Natural Gas | $92,617 | 13,708 |
MMBtu
|
$6.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,368 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,538 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $875 | $729 |
$741
8,206
kWh
|
$134
-
kW-mo/yr
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $794 | $462 |
$688
7,620
kWh
|
$106
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $301 | $960 |
$244
2,638
kWh
|
$57
-
kW-mo/yr
|
- | - | - | |
04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $7,998 | $13,780 | - | - |
$7,998
-
MMBtu
|
- | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,869 | - | - | - |
$6,869
-
MMBtu
|
- | - | |
06 | 2.2511: Insulate bare equipment | $649 | $558 | - | - |
$649
-
MMBtu
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,018 | $1,475 |
$1,833
20,223
kWh
|
$185
-
kW-mo/yr
|
- | - | - | |
08 | 3.4111: Use closed cycle process to minimize waste water production | $1,670 | $2,818 | - | - | - |
$1,670
-
Tgal
|
- | |
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,899 | $6,395 | - | - | - | - |
$5,899
-
lb
|
|
10 | 3.4155: Meter waste water | $14,295 | $4,500 | - | - | - |
$14,295
-
Tgal
|
- | |
TOTAL RECOMMENDED | $41,368 | $31,677 |
$3,506
38,687
kWh
|
$482
-
kW-mo/yr
|
$15,516
-
MMBtu
|
$15,965
-
Tgal
|
$5,899
-
lb
|
||
TOTAL IMPLEMENTED | $8,538 | $1,191 |
$1,429
15,826
kWh
|
$240
-
kW-mo/yr
|
$6,869
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs